Table 4
| Location. | Number of days worked. | Total length of heading, in feet. | Average length of heading driven per day worked, in feet. |
| N.E. | 227 | 446 | 1.96 |
| S.E. | 168 | 346 | 2.06 |
| N.W. | 272 | 768 | 2.82 |
| S.W. | 234 | 698 | 2.98 |
Progress at Hackensack.—At Hackensack the total number of days worked on the tunnels proper, all in trap rock (omitting the cut and cover) was about 792, divided as shown in Table 5.