Table 6

Title.Day.Night.
No.Rate.Amount.No.Rate.Amount.
Walking bosses2$5.00$10.00
Timekeeper23.006.00
Watchmen5$2.00$10.00
Waterboys11.501.50
Carpenter foremen23.507.0014.004.00
Carpenters142.5035.0082.5020.00
Pipe-fitters13.003.00
Pipe-fitter’s helper11.751.75
Wheelwright12.752.75
Wheelwright’s helper11.751.75
Blacksmith13.003.00
Blacksmith’s helper11.751.75
Foremen riggers13.003.00
Riggers61.7510.50
Foremen trackmen13.003.00
Trackmen61.509.00
Machinist23.006.00
Machinist’s helper11.751.75
Electrician23.006.0012.502.50
Electrician’s helper11.751.75
Lampman11.501.50
Pumpman11.501.50
Finishers32.507.50
Hoist engineers123.0036.00
Dinky engineers52.7513.7512.752.75
Brakemen51.758.7511.751.75
Switchmen11.501.50
Barnmen12.002.0012.502.50
Drivers91.5013.50
Foremen ductmen22.502.50
Ductmen52.0010.00
Foremen laborers133.5045.5023.507.00
Laborers1201.75210.00201.7535.00
Compressor engineer13.503.5013.503.50
Firemen22.505.0012.502.50
Oiler11.751.75
Coal passers21.753.5011.751.75
Totals334$469.7550$108.25
Total daily labor expense$578.00

The water finding its way into the side ditches in the approach, which of course included all rain falling in this area, was intercepted just inside the portal and carried back to the mouth of the cut through 24-in. cast-iron pipes laid beneath the conduits in the central bench-wall, thus disposing by natural drainage of a not inconsiderable quantity of water which would otherwise have flowed through the tunnels to the sump at the Weehawken Shaft, from which it would have had to be pumped to the surface.

About 100 ft. of the tunnel immediately east of the Hackensack Portal was built by the cut-and-cover method, and the arch section used in the tunnel was modified by widening the haunches, the thickness of the arch at the crown being gradually increased from 22 in. at the portal, Station 324, to 34 in. at Station 323, where the regular segmental timbering at the tunnel commenced. A general view of the approach during construction is shown by Fig. 1, Plate XXV.