Table 1
Shifts: Number of shifts covered by observations.
Hours: Average number of hours worked per shift.
D/Hr: Average depth drilled per hour per drill
D/Yd: Average depth drilled per yard.
Hack.: Hackensack
Whk.: Weehawken
Cs: Central Shaft
| Method. | Date. | Shifts | Place. | Hours | D/Hr | D/Yd | |
| No. 1— 4-drill | Aug. ’06 | 44 | Hack., | N. | 5.69 | 2.78 | 10.1 |
| Sept. ’06 | 38 | ″ | N. | 5.80 | 3.77 | 11.1 | |
| Aug. ’06 | 43 | ″ | S. | 5.60 | 2.89 | 9.1 | |
| Sept. ’06 | 36 | ″ | S. | 6.18 | 2.65 | 8.7 | |
| Jan. ’07 | 16 | CS E. | N. | 5.99 | 2.99 | 8.2 | |
| Jan. ’07 | 20 | ″ | S. | 6.05 | 2.9 | 7.1 | |
| Apr. ’07 | 48 | CS W. | N. | 4.92 | 3.3 | 6.7 | |
| Apr. ’07 | 48 | ″ | S. | 5.00 | 3.2 | 7.7 | |
| Nos. 2 and 3— 5-drill | Dec. ’06 | 54 | Whk., | N. | 4.95 | 2.16 | 4.52 |
| Dec. ’06 | 54 | ″ | S. | 5.23 | 2.14 | 4.54 | |
| Dec. ’06 | 52 | Hack., | N. | 5.03 | 2.2 | 5.77 | |
| Dec. ’06 | 54 | ″ | S. | 5.90 | 1.82 | 5.67 | |
| No. 4— 7-drill | June ’07 | 56 | Whk., | N. | 4.77 | 2.55 | 4.23 |
| June ’07 | 58 | ″ | S. | 4.82 | 2.26 | 3.88 | |
| 8-drill | May ’07 | 60 | Hack., | N. | 4.67 | 2.44 | 5.00 |
| May ’07 | 60 | ″ | S. | 4.54 | 2.57 | 4.80 | |